Question 31 - PRINCE2-7-Foundation discussion

Report
Export

What is the definition of a project outcome?

A.
A measurable improvement that is perceived as an advantage by one or more stakeholders
Answers
A.
A measurable improvement that is perceived as an advantage by one or more stakeholders
B.
The reason for the project
Answers
B.
The reason for the project
C.
The result of the change derived from using the project's outputs
Answers
C.
The result of the change derived from using the project's outputs
D.
The project's specialist products.
Answers
D.
The project's specialist products.
Suggested answer: C

Explanation:

According to PRINCE2, a project outcome is defined as the result of the change derived from utilizing the project's outputs. Outcomes are what the project seeks to achieve which may involve a change in the way an organization operates.

Reference: PRINCE2 Foundation official guide and study material.