What needs to be in place to ensure effective issue and change control?

A.
Configuration management system
Answers
A.
Configuration management system
B.
Manage by exception
Answers
B.
Manage by exception
C.
Quality planning
Answers
C.
Quality planning
D.
Information needs for stakeholders
Answers
D.
Information needs for stakeholders
Suggested answer: A

Explanation:

Effective issue and change control within a PRINCE2 project relies heavily on a configuration management system. This system tracks all items of the project, including their versions and changes, allowing for controlled changes and ensuring that all items are identified, accounted for, and monitored throughout the project.

Reference: PRINCE2 Foundation official study guide and online resources.