Which should be funded by a change budget?

A.
Increase in agreed scope
Answers
A.
Increase in agreed scope
B.
Initiation stage
Answers
B.
Initiation stage
C.
Change Authority
Answers
C.
Change Authority
D.
Handover activities
Answers
D.
Handover activities
Suggested answer: A

Explanation:

The change budget in a PRINCE2 project is designed to fund changes that involve an increase in the agreed scope of the project. Such changes typically require additional budget allocations as they extend or modify what the project initially planned to deliver.

Reference: PRINCE2 Foundation official study guide and online resources.