Question 41 - PRINCE2-7-Foundation discussion
Which should be funded from a change budget?
A.
The Starting up a Project process
B.
A fallback plan
C.
An agreed change to the scope of a project
D.
A change to a plan, within allocated tolerances, due to poor estimating