Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

A.
Only 1 is true
Answers
A.
Only 1 is true
B.
Only 2 is true
Answers
B.
Only 2 is true
C.
Both 1 and 2 are true
Answers
C.
Both 1 and 2 are true
D.
Neither 1 or 2 are true
Answers
D.
Neither 1 or 2 are true
Suggested answer: B

Explanation:

The statement that 'The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved' is true. This process is crucial for ensuring that the project has met its objectives and that all remaining project deliverables are acceptable to stakeholders. The first statement is incorrect as the receipt of completed Work Packages is typically handled during the 'Managing a Stage Boundary' process rather than in the 'Closing a Project' process.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources