What takes place during the Closing a Project process?

A.
The post-project benefits reviews are performed
Answers
A.
The post-project benefits reviews are performed
B.
Ownership of the project's products is transferred to the customer
Answers
B.
Ownership of the project's products is transferred to the customer
C.
An End Stage Report is prepared for the final stage
Answers
C.
An End Stage Report is prepared for the final stage
D.
The project closure notification is reviewed and approved
Answers
D.
The project closure notification is reviewed and approved
Suggested answer: B

Explanation:

During the Closing a Project process in PRINCE2, the ownership of the project's products is formally transferred to the customer, ensuring that all deliverables have been accepted and are ready for operational use. This transfer marks the formal completion of the project.

Reference: PRINCE2 Foundation official study guide and materials.