Question 54 - PRINCE2-7-Foundation discussion
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A.
Directing a Project
B.
Managing a Stage Boundary
C.
Controlling a Stage
D.
Starting up a Project