Question 55 - PRINCE2-7-Foundation discussion
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
A.
Managing a Stage Boundary
B.
Managing Product Delivery
C.
Closing a Project
D.
Controlling a Stage
Your answer: