What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A.
Directing a Project
Answers
A.
Directing a Project
B.
Controlling a Stage
Answers
B.
Controlling a Stage
C.
Managing a Stage Boundary
Answers
C.
Managing a Stage Boundary
D.
Managing Product Delivery
Answers
D.
Managing Product Delivery
Suggested answer: B

Explanation:

The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage's products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.

Reference: PRINCE2 Foundation official documentation and study materials.