In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

A.
Product Description
Answers
A.
Product Description
B.
Team Plan
Answers
B.
Team Plan
C.
Work Package
Answers
C.
Work Package
D.
Stage Plan
Answers
D.
Stage Plan
Suggested answer: C

Explanation:

In PRINCE2, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.