Question 60 - PRINCE2-7-Foundation discussion

Report
Export

Which is a purpose of the Directing a Project process?

A.
Provide the information required to confirm if it is worthwhile to initiate a project
Answers
A.
Provide the information required to confirm if it is worthwhile to initiate a project
B.
Enable overall control of a project to be exercised by the Project Board
Answers
B.
Enable overall control of a project to be exercised by the Project Board
C.
Establish the level of control required by the Project Board after initiation.
Answers
C.
Establish the level of control required by the Project Board after initiation.
D.
Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Answers
D.
Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Suggested answer: B

Explanation:

The purpose of the Directing a Project process in PRINCE2 is to enable the Project Board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This ensures that the Project Board can make key decisions and remain accountable for the project's success while not being involved in the lower-level, day-to-day activities.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources