Which is an objective of the Directing a Project process?

A.
Create and authorize the project mandate
Answers
A.
Create and authorize the project mandate
B.
Provide management control and direction
Answers
B.
Provide management control and direction
C.
Control the day-to-day running of the project
Answers
C.
Control the day-to-day running of the project
D.
Provide accurate progress information to the Project Manager
Answers
D.
Provide accurate progress information to the Project Manager
Suggested answer: B

Explanation:

An objective of the Directing a Project process is to provide management control and direction for the project. This involves making strategic decisions, providing overall guidance to the Project Manager, and ensuring the project remains aligned with organizational objectives and capable of delivering the benefits defined in the Business Case.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources