In what process is the authorization to deliver the project's products given?

A.
Starting up a Project
Answers
A.
Starting up a Project
B.
Initiating a Project
Answers
B.
Initiating a Project
C.
Managing a Stage Boundary
Answers
C.
Managing a Stage Boundary
D.
Directing a Project
Answers
D.
Directing a Project
Suggested answer: D

Explanation:

The authorization to deliver the project's products is given during the Directing a Project process. This process involves the Project Board's decision-making responsibilities, including granting permission to proceed with the project after the initiation phase and authorizing the delivery of stages as the project progresses.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources