Question 65 - PRINCE2-7-Foundation discussion
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
A.
Only 1 is true
B.
Only 2 is true
C.
Both 1 and 2 are true
D.
Neither 1 or 2 are true