Which is an objective of the Initiating a Project process?

A.
Develop the corporate quality management system as part of the Project Initiation Documentation
Answers
A.
Develop the corporate quality management system as part of the Project Initiation Documentation
B.
Prepare the plans for the subsequent stages
Answers
B.
Prepare the plans for the subsequent stages
C.
Summarize how the organization's project management method will be tailored for the project
Answers
C.
Summarize how the organization's project management method will be tailored for the project
D.
Request authority from corporate management to deliver the project
Answers
D.
Request authority from corporate management to deliver the project
Suggested answer: C

Explanation:

One of the key objectives of the Initiating a Project process is to tailor the organization's project management method to suit the specific requirements of the project. This involves adapting processes, controls, roles, responsibilities, and techniques to ensure they are appropriate for the project's context.

Reference: PRINCE2 Foundation official documentation and study materials.