Which is NOT a purpose of the Initiating a Project process?

A.
Enable a Project Board decision about the commitment of resources to a project
Answers
A.
Enable a Project Board decision about the commitment of resources to a project
B.
Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
Answers
B.
Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
C.
Establish solid foundations for a project
Answers
C.
Establish solid foundations for a project
D.
Enable the Project Board to decide whether it is worthwhile to initiate a project
Answers
D.
Enable the Project Board to decide whether it is worthwhile to initiate a project
Suggested answer: D

Explanation:

This statement is not true as the purpose of the Initiating a Project process. The correct purpose of this process is to ensure that there are solid foundations for the project, usually after the project has already been decided as worthwhile and approved for initiation. The decision to initiate a project is typically made before the Initiating a Project process.

Reference: PRINCE2 Foundation official documentation and study materials.