Which plan provides the Business Case with costs during the Initiating a Project process?

A.
Initiation Stage Plan
Answers
A.
Initiation Stage Plan
B.
Project Plan
Answers
B.
Project Plan
C.
Stage Plan
Answers
C.
Stage Plan
D.
Team Plan
Answers
D.
Team Plan
Suggested answer: B

Explanation:

During the Initiating a Project process in PRINCE2, the Project Plan provides the Business Case with necessary details, including cost estimates. This plan outlines the overall scope and timing of the project and sets the baseline for project management activities, including cost control.