Question 76 - PRINCE2-7-Foundation discussion
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
A.
Closing a Project
B.
Managing a Stage Boundary
C.
Managing Product Delivery
D.
Directing a Project