Which two roles are linked by the Managing Product Delivery process?

A.
Corporate or programme management and Project Board
Answers
A.
Corporate or programme management and Project Board
B.
Project Board and Project Manager
Answers
B.
Project Board and Project Manager
C.
Project Manager and Team Manager
Answers
C.
Project Manager and Team Manager
D.
Team Manager and external supplier
Answers
D.
Team Manager and external supplier
Suggested answer: C

Explanation:

The Managing Product Delivery process in PRINCE2 links the Project Manager and Team Manager roles. This connection is crucial as the Project Manager assigns work to the Team Manager, who is responsible for the production of the project's products, ensuring that the work is done to the right quality, at the right time, and within cost constraints.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

=========================