When should the Project Board refer to corporate or programme management for a decision?

A.
The stage requires resources
Answers
A.
The stage requires resources
B.
It is forecast that project level tolerance will be exceeded
Answers
B.
It is forecast that project level tolerance will be exceeded
C.
The Senior Supplier or Senior User needs to be changed
Answers
C.
The Senior Supplier or Senior User needs to be changed
D.
Any request for change needs to be approved
Answers
D.
Any request for change needs to be approved
Suggested answer: B

Explanation:

The Project Board should refer to corporate or programme management for decisions when it is forecast that the project level tolerance will be exceeded. This scenario typically triggers an exception process as the predefined tolerances are fundamental limits within which the Project Board allows the Project Manager to manage the project.

Reference: PRINCE2 Foundation official study guide and materials.