Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

A.
Stage Plan
Answers
A.
Stage Plan
B.
Communication Management Strategy
Answers
B.
Communication Management Strategy
C.
Follow-on action recommendations
Answers
C.
Follow-on action recommendations
D.
Quality Management Strategy
Answers
D.
Quality Management Strategy
Suggested answer: B

Explanation:

The Communication Management Strategy should be referred to at the end of a stage to check whether there is a requirement to send copies of the End Stage Report to external interested parties. This document outlines how, when, and by whom information will be disseminated throughout the project, including communication with external stakeholders.

Reference: PRINCE2 Foundation official study guide and materials.