Which is NOT a purpose of the Organization theme?

A.
Define a project management team structure
Answers
A.
Define a project management team structure
B.
Define the level of tolerance for each level of the project management team
Answers
B.
Define the level of tolerance for each level of the project management team
C.
Define the Project Board's responsibility for directing the project
Answers
C.
Define the Project Board's responsibility for directing the project
D.
Define which role is accountable for the project's success
Answers
D.
Define which role is accountable for the project's success
Suggested answer: B

Explanation:

The Organization theme does not include defining the level of tolerance for each level of the project management team. Tolerance levels are typically set within the Plans theme, which deals with how the project is structured in terms of stages and the delegation of authority within those tolerances. The Organization theme primarily focuses on defining roles and responsibilities.

Reference: PRINCE2 Foundation official study guide and materials.