Which does the Executive need to ensure is in place before the project is initiated?

A.
All Work Packages are authorized
Answers
A.
All Work Packages are authorized
B.
An understanding of how the project will contribute to corporate objectives
Answers
B.
An understanding of how the project will contribute to corporate objectives
C.
The Project Plan has been approved
Answers
C.
The Project Plan has been approved
D.
The Project Initiation Documentation is complete
Answers
D.
The Project Initiation Documentation is complete
Suggested answer: B

Explanation:

Before initiating a project, the Executive in PRINCE2 needs to ensure there is a clear understanding of how the project will contribute to the corporate objectives. This alignment is crucial for justifying the project's existence and ensuring it has a clear business purpose and expected benefits that support the organization's strategic goals.