List of questions
Related questions
Question 85 - PRINCE2-7-Foundation discussion
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
A.
Executive
B.
Senior User
C.
Senior Supplier
D.
Project Manager
Your answer: