Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A.
quality
Answers
A.
quality
B.
supplier
Answers
B.
supplier
C.
risk
Answers
C.
risk
D.
product
Answers
D.
product
Suggested answer: A

Explanation:

A member of the Project Board is responsible for quality assurance in PRINCE2. Quality assurance is concerned with ensuring that the project's products meet the quality requirements set out in the project and that the project adheres to the appropriate corporate, programme management, or customer quality standards.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources