How many roles make up the Project Board?

A.
One
Answers
A.
One
B.
Two
Answers
B.
Two
C.
Three
Answers
C.
Three
D.
Four
Answers
D.
Four
Suggested answer: C

Explanation:

The Project Board within the PRINCE2 framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier interests respectively, ensuring that the project's decision-making is balanced across these three perspectives.

Reference: PRINCE2 Foundation official documentation and study materials.