Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.
Corporate or programme management
Answers
A.
Corporate or programme management
B.
Project Board
Answers
B.
Project Board
C.
Project Manager
Answers
C.
Project Manager
D.
Team Manager
Answers
D.
Team Manager
Suggested answer: B

Explanation:

The approval needed to replace a Stage Plan with an Exception Plan must come from the Project Board. This is because the Exception Plan is created when a Stage Plan is forecast to exceed its tolerance levels, and the Project Board is responsible for approving such significant changes in the project's direction or management.

Reference: PRINCE2 Foundation official documentation and study materials.