Which statement applies to Stage Plans?

A.
Always have the same duration as the Project Plan
Answers
A.
Always have the same duration as the Project Plan
B.
Are produced at the same time as the Project Initiation Documentation
Answers
B.
Are produced at the same time as the Project Initiation Documentation
C.
Assist the Project Manager in the day-to-day running and control of the project
Answers
C.
Assist the Project Manager in the day-to-day running and control of the project
D.
Provide a baseline against which the Project Board monitor overall progress
Answers
D.
Provide a baseline against which the Project Board monitor overall progress
Suggested answer: C

Explanation:

Stage Plans in PRINCE2 are essential tools for the Project Manager, assisting in the day-to-day management and control of the project. Each Stage Plan provides the detail needed for each management stage of the project, including what work will be done, when it will be delivered, and who will be involved, thus facilitating effective project governance on a stage-by-stage basis. They do not necessarily match the duration of the Project Plan or get produced simultaneously with the Project Initiation Documentation.

Reference: PRINCE2 7 Foundation handbook and other official documents.