Why is the 'initiating a project' process used?

A.
To decide which project approach is suitable for the project
Answers
A.
To decide which project approach is suitable for the project
B.
To fully understand how the project objectives will be achieved before committing significant resources
Answers
B.
To fully understand how the project objectives will be achieved before committing significant resources
C.
To produce the required work packages
Answers
C.
To produce the required work packages
D.
To enable corporate or programme management to give authorization to deliver a project
Answers
D.
To enable corporate or programme management to give authorization to deliver a project
Suggested answer: B

Explanation:

The 'Initiating a Project' process in PRINCE2 is crucial for establishing a solid foundation for the project. This process is used to ensure that there is a shared understanding of the reasons for undertaking the project, the way its objectives will be achieved, and the related commitments of time and resources before substantial resources are committed.

Reference: PRINCE2 7 Foundation Handbook and official training materials.