Question 137 - PRINCE2-7-Foundation discussion
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
A.
change budget
B.
project budget
C.
project's cost tolerance
D.
project's risk tolerance
Your answer: