Which is a purpose of a Risk Register?

A.
Capture risks that may occur during the project
Answers
A.
Capture risks that may occur during the project
B.
Record how risk management activities will be undertaken on the project
Answers
B.
Record how risk management activities will be undertaken on the project
C.
Record the risk tolerance for the project
Answers
C.
Record the risk tolerance for the project
D.
Capture issues which are impacting on the delivery of the project objectives
Answers
D.
Capture issues which are impacting on the delivery of the project objectives
Suggested answer: A

Explanation:

The purpose of a Risk Register in PRINCE2 is to capture all the risks that may impact the project throughout its duration. It serves as a tool to document the details of each identified risk, including their nature, potential impact, and proposed responses. This register is continuously updated as new risks are identified and as existing risks evolve or are resolved.

Reference: PRINCE2 7 Foundation handbook and official documents.