Which role is responsible for ensuring the project is justified in terms of cost?

A.
Project manager
Answers
A.
Project manager
B.
Executive
Answers
B.
Executive
C.
Senior user
Answers
C.
Senior user
D.
Senior supplier
Answers
D.
Senior supplier
Suggested answer: B

Explanation:

In PRINCE2, the Executive role is responsible for ensuring that the project is justifiable in terms of cost. This includes making decisions about whether the project remains viable and desirable within its cost constraints. The Executive is tasked with the overall direction and management of the project from a business perspective, ensuring that it delivers value for money.

Reference: PRINCE2 7 Foundation resources and materials.