Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A.
Controlling a Stage
Answers
A.
Controlling a Stage
B.
Closing a Project
Answers
B.
Closing a Project
C.
Directing a Project
Answers
C.
Directing a Project
D.
Managing a Stage Boundary
Answers
D.
Managing a Stage Boundary
Suggested answer: D

Explanation:

The Managing a Stage Boundary process provides the Project Board with information necessary to review the success of the current stage and decide whether there remains a justified business reason to continue with the project. This process includes the evaluation of the stage's performance and the ongoing viability of the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.