What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: B

Explanation:

As part of the 'controlling a stage' process, the actions taken include authorizing work to be done (2) and taking corrective action (3) as necessary to manage the stage effectively and keep the project on track.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.