What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
A.
1 and 2
B.
2 and 3
C.
3 and 4
D.
1 and 4
Your answer: