Which is a key decision made during the 'directing a project' process?

A.
Select and appoint the project executive
Answers
A.
Select and appoint the project executive
B.
Approve the project manager role description
Answers
B.
Approve the project manager role description
C.
Confirm that the benefits management approach addresses all expected benefits
Answers
C.
Confirm that the benefits management approach addresses all expected benefits
D.
Approve the proposed project mandate
Answers
D.
Approve the proposed project mandate
Suggested answer: C

Explanation:

A key decision made during the 'directing a project' process is to confirm that the benefits management approach addresses all expected benefits. This ensures that the project is aligned with its intended outcomes and that all potential benefits are adequately planned for and tracked.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.