Why is a project brief produced?

A.
To act as a trigger for the 'starting up a project' process
Answers
A.
To act as a trigger for the 'starting up a project' process
B.
To record the how the project will communicate with its stakeholders
Answers
B.
To record the how the project will communicate with its stakeholders
C.
To provide a full and firm foundation for the initiation of a project
Answers
C.
To provide a full and firm foundation for the initiation of a project
D.
To be used by the project board as a basis for reviewing the progress of a project
Answers
D.
To be used by the project board as a basis for reviewing the progress of a project
Suggested answer: C

Explanation:

A project brief is produced to provide a full and firm foundation for the initiation of a project. It outlines the project objectives, scope, constraints, and the project management team structure, setting the stage for detailed planning and initiation activities.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.