Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

A.
are below the agreed change budget
Answers
A.
are below the agreed change budget
B.
are objected to by team members
Answers
B.
are objected to by team members
C.
are rejected by the change authority
Answers
C.
are rejected by the change authority
D.
exceed the agreed change budget
Answers
D.
exceed the agreed change budget
Suggested answer: D

Explanation:

When proposed changes exceed the agreed change budget, the change authority must refer the decision back to the Project Board. This is because changes that exceed the budget may impact the overall project constraints and require higher-level approval to proceed.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.