Question 155 - PRINCE2-7-Foundation discussion

Report
Export

Which is a purpose of the change theme?

A.
To prevent change to baselined products
Answers
A.
To prevent change to baselined products
B.
To identify, assess and control any potential and approved changes to baselined products
Answers
B.
To identify, assess and control any potential and approved changes to baselined products
C.
To establish mechanisms to monitor and compare actual achievements against those planned
Answers
C.
To establish mechanisms to monitor and compare actual achievements against those planned
D.
To assess and control uncertainty
Answers
D.
To assess and control uncertainty
Suggested answer: B

Explanation:

The purpose of the Change theme in PRINCE2 is to identify, assess, and control any potential and approved changes to baselined products. This theme provides the mechanisms to manage and control changes, which may affect the project's agreed-upon scope, products, timescales, or costs. It ensures that all changes are assessed for their impact and only implemented with appropriate approvals.

Reference: PRINCE2 7 Foundation resources and materials.