List of questions
Related questions
Question 154 - PRINCE2-7-Foundation discussion
How is the tailoring approach defined for a project?
A.
The project board approves the approach
B.
The project board documents the approach
C.
Project assurance approves the approach
D.
Project assurance documents the approach
Your answer:
0 comments
Sorted by
Leave a comment first