Question 154 - PRINCE2-7-Foundation discussion

Report
Export

How is the tailoring approach defined for a project?

A.
The project board approves the approach
Answers
A.
The project board approves the approach
B.
The project board documents the approach
Answers
B.
The project board documents the approach
C.
Project assurance approves the approach
Answers
C.
Project assurance approves the approach
D.
Project assurance documents the approach
Answers
D.
Project assurance documents the approach
Suggested answer: A

Explanation:

The tailoring approach for a project is defined and approved by the project board. This includes adapting PRINCE2 to suit the project's environment, size, complexity, importance, capability, and risk. Tailoring is crucial to ensuring that the project management method is applied in a way that fits the specific characteristics of the project and its context.

Reference: PRINCE2 7 Foundation handbook and documents.