What is the project manager role responsible for?

A.
Approving the completion of each management stage
Answers
A.
Approving the completion of each management stage
B.
Ensuring that the project produces the required products
Answers
B.
Ensuring that the project produces the required products
C.
Defining the project-level tolerances
Answers
C.
Defining the project-level tolerances
D.
Verifying that the project gives value for money
Answers
D.
Verifying that the project gives value for money
Suggested answer: B

Explanation:

The Project Manager role in PRINCE2 is primarily responsible for ensuring that the project produces the required products, to the defined standards of quality and within the specified constraints of time and cost. This central responsibility involves coordinating all project activities and resources to achieve the project objectives.

Reference: PRINCE2 7 Foundation resources and materials.