Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.
Progress
Answers
A.
Progress
B.
Change
Answers
B.
Change
C.
Organization
Answers
C.
Organization
D.
Quality
Answers
D.
Quality
Suggested answer: A

Explanation:

The Progress theme provides all management levels within the project management team with mechanisms for monitoring and control. This theme ensures that there are clear benchmarks for performance and mechanisms in place to assess progress throughout the project's life cycle.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.