Question 168 - PRINCE2-7-Foundation discussion

Report
Export

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

A.
the 'starting up a project' process is completed
Answers
A.
the 'starting up a project' process is completed
B.
the project mandate has been approved by the project board
Answers
B.
the project mandate has been approved by the project board
C.
the project board has agreed the project strategies
Answers
C.
the project board has agreed the project strategies
D.
corporate, programme management or the customer have authorized a project
Answers
D.
corporate, programme management or the customer have authorized a project
Suggested answer: A

Explanation:

The 'Directing a Project' process in PRINCE2 starts when the 'Starting up a Project' process is completed. This transition is triggered by the request to initiate a project. At this point, the project has been preliminarily assessed, and a project brief and initiation documentation are ready to be developed during the 'Initiating a Project' process, pending authorization from the Project Board to proceed.

Reference: PRINCE2 7 Foundation handbook and official documents.