Question 169 - PRINCE2-7-Foundation discussion

Report
Export

Which process is used to define how baselines will be established and controlled?

A.
Controlling a stage
Answers
A.
Controlling a stage
B.
Directing a project
Answers
B.
Directing a project
C.
Initiating a project
Answers
C.
Initiating a project
D.
Starting up a project
Answers
D.
Starting up a project
Suggested answer: C

Explanation:

The process used to define how baselines will be established and controlled is 'Initiating a Project'. During this process, the project's management strategies, including quality, risk, communication, and configuration management strategies, are defined. These strategies include how baselines for the project's products and plans will be established and controlled throughout the project lifecycle.

Reference: PRINCE2 7 Foundation resources and study materials.