Which describes a risk event?

A.
The area of uncertainty in terms of the threat or opportunity
Answers
A.
The area of uncertainty in terms of the threat or opportunity
B.
The derivation or sources of a potential risk to the project
Answers
B.
The derivation or sources of a potential risk to the project
C.
The achievement of a milestone on the project plan
Answers
C.
The achievement of a milestone on the project plan
D.
The sequence of events and actions that will be put in place if a risk occurs
Answers
D.
The sequence of events and actions that will be put in place if a risk occurs
Suggested answer: A

Explanation:

A risk event in PRINCE2 is described as the area of uncertainty in terms of the threat or opportunity. It specifically refers to a specific set of circumstances that may occur and impact the project if the risk materializes. This description encapsulates the nature of a risk as being either a potential threat or an opportunity based on uncertain events that might affect project objectives.

Reference: PRINCE2 7 Foundation handbook and official documents.