Question 177 - PRINCE2-7-Foundation discussion

Report
Export

Which is a minimum requirement for applying the plans theme?

A.
The project must have at least two management stages
Answers
A.
The project must have at least two management stages
B.
The team managers in the project must prepare team plans
Answers
B.
The team managers in the project must prepare team plans
C.
Scope tolerance must be prioritized using MoSCoW
Answers
C.
Scope tolerance must be prioritized using MoSCoW
D.
The project plan must be presented as a Gantt chart
Answers
D.
The project plan must be presented as a Gantt chart
Suggested answer: B

Explanation:

A minimum requirement for applying the Plans theme in PRINCE2 is that team managers in the project must prepare team plans. This ensures that each part of the project controlled by a team manager is adequately planned in line with the overall project plan and stage plans. These team plans provide detailed guidance on how products will be delivered within the constraints set by the project management.

Reference: PRINCE2 7 Foundation resources and study materials.