ExamGecko
Question list
Search
Search

Question 179 - PRINCE2-7-Foundation discussion

Report
Export

Which level of management sets the project level tolerances?

A.
Project board
Answers
A.
Project board
B.
Team manager
Answers
B.
Team manager
C.
Corporate, programme management or the customer
Answers
C.
Corporate, programme management or the customer
D.
Project manager
Answers
D.
Project manager
Suggested answer: C

Explanation:

The level of management that sets the project level tolerances in PRINCE2 is corporate, programme management, or the customer. These project-level tolerances are defined to set the allowable limits of variation for the project's objectives, which the Project Manager must work within. This helps ensure that the project remains aligned with strategic goals and customer or corporate standards.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
NAKAYAMA HIROYUKI
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first