Identify the missing word in the following sentence.

A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

A.
benefits
Answers
A.
benefits
B.
dis-benefits
Answers
B.
dis-benefits
C.
issues
Answers
C.
issues
D.
risks
Answers
D.
risks
Suggested answer: A

Explanation:

In PRINCE2, a project's benefits are defined as the measurable improvements that result from the outcomes achieved through the use of the project's outputs. These benefits should align with the objectives set out in the business case and are an essential part of the project's value proposition.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.