Question 181 - PRINCE2-7-Foundation discussion

Report
Export

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

A.
Appointing the project board and producing the project brief
Answers
A.
Appointing the project board and producing the project brief
B.
Planning the initiation stage and appointing the project manager
Answers
B.
Planning the initiation stage and appointing the project manager
C.
Producing the additional role descriptions and validating the project product description
Answers
C.
Producing the additional role descriptions and validating the project product description
D.
Verifying the project approach and capturing previous lessons
Answers
D.
Verifying the project approach and capturing previous lessons
Suggested answer: D

Explanation:

If a project is part of a programme, the activities related to verifying the project approach and capturing previous lessons in the 'Starting up a Project' process are most likely to be reduced or eliminated. This reduction occurs because the programme likely provides a strategic framework and lessons learned that the project can adopt directly.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.