Which process provides information for the project board to review a completed stage and confirm continued business justification?

A.
Controlling a stage
Answers
A.
Controlling a stage
B.
Closing a project
Answers
B.
Closing a project
C.
Directing a project
Answers
C.
Directing a project
D.
Managing a stage boundary
Answers
D.
Managing a stage boundary
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 is designed to provide the project board with information to review the performance of a completed stage, confirm the continued business justification, and decide whether to proceed with the next stage. This process includes preparing key documents such as the End Stage Report and the next Stage Plan.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.