Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: A

Explanation:

The advantages of having a clear end to a project include ensuring that no further costs are incurred by the project (1) and that project products are transferred to operations and support for ongoing use (2). The achievement of all benefits at project closure (3) is not guaranteed and typically occurs post-project, and the project brief is not re-baselined at project end (4).

Reference: PRINCE2 Foundation Handbook, Closing a Project section.